Paving Program

The Street Reconstruction Program (Paving)

 

Work under the program will occur between April and October 2017. Please refer to the UPDATES section of this page to learn the latest news, delays and information regarding the paving project.

The streets scheduled to be paved and the type of work being done on them this year can be found on the list below.

Mill/Fill (remove top layer of pavement and repave)
Beltline from the North Ave Ramps to Colchester, including ramps at Plattsburg Ave
East Ave from Main Street to Colchester Ave
Manhattan Drive from Rose Street to Park street
 
Reclaim (Grind up road to dirt, reshape, and repave)
Hildred Drive  (Circle portion)
Marble Ave
Valade
Borestone Drive
Rivers Edge Drive
King Street (from Battery to Pine)

 

STAY INFORMED

If you would like to be kept up to date on changes, delays and other occurrences please send us your name and email so that we may add you to our listserv for construction updates.

Or Like us on Facebook! Remember to change under the Like button to set it to See First to see information in your News Feed.

If you have any questions about our paving program or the list above, please contact me directly at LWheelock@burlingtonvt.gov or 802-540-0397.

For Abutting Property Owners (Reclaim Streets):

Any property owner or utility company has until June 30st, 2017 to complete or schedule any subsurface work that they plan to perform on one of the streets listed above.  If completed or scheduled, this work will be subject only to the administrative and inspection portion of the street excavation fee.  A full excavation fee will be waived for property owners who schedule or complete utility upgrades, such as water or sewer work prior to June 30, 2017. Any property on adjacent streets is eligible for this waiver only if their utility service connections originate on one of the listed streets.

To the extent it is feasible, we will try to accommodate your work schedule with ours. No construction permits involving excavations within the City’s right-of-way will be issued on a street listed above after the City has completed this year’s paving project.  It is important that you notify us if you have any plans (Which may include replacing and existing or installing a new sewer, water, gas, communication or buried electrical service).  Please call DPW with question or to schedule work at 863-9094.

Photos below show galvanized waterline and flow restricting corrosion overtime:

 

Photos below show corroded sewer lines from house to the main (photos from Oakland Terrace 2015):

 

SCHEDULE:

NOVEMBER 2017: 2018 Street Reconstruction Program street list approved by Public Works Commission.

11/30/17: Notices went out to property owners and residents

 

 