Burlington Parks, Recreation & Waterfront seeks a qualified contractor to provide and install an inspired selection of playground features appropriate for 2-to-5 year-olds.

The selected contractor shall provide all materials, labor and equipment to complete installation of the following:

  • Equipment included in the proposals should demonstrate a review of other equipment available within the playground area shown in Exhibit B. The new structure should avoid providing opportunities for play that duplicate existing equipment.
  • Layout and equipment must comply with ADA Accessibility Standards for playgrounds and preferably, will demonstrate incorporation of Universally Accessible Design.
  • All equipment must conform to ASTM 1487-11.
  • Provide depth specifications for safety surfacing in compliance with ASTM F2223. BPRW will procure and install engineered wood fiber according to depth and schedule specified.
  • No flexible climbers using encapsulated or coated chain.
  • No suspended stepping stone balance climbers.

The allocated budget for this project is $22,500.

See attached RFP document for complete details.

 

ANTICIPATED PROJECT SCHEDULE

  • Issued: Wednesday, May 4, 2022
  • Questions Due: Monday, May 16, 2022
  • Proposals Due: Monday, May 23, 2022
  • Anticipated Notice of Award: Week of June 6, 2022
  • Contract Signing: June 7, 2022
  • Construction Complete: No later than October 31, 2022

SUBMISSIONS

Proposals and questions shall be submitted via e-mail to:
Max Madalinski, Parks Project Coordinator
Burlington Parks, Recreation & Waterfront
mmadalinski@burlingtonvt.gov
(802) 881-4000

City Department: 
Parks, Recreation & Waterfront
RFP Deadline: 
Monday, May 23, 2022