Menu

Calahan Park Playground Replacement

The existing playground at Calahan Park is approximately 37 years old and Burlington Parks Recreation and Waterfront seeks to hire a contractor to design and install a replacement playground. BPRW will remove this equipment prior to contractor construction. The selected contractor will provide the City with professional services to realize the successful implementation of all aspects of this project. The contractor will be responsible for coordinating work with any sub-contractors. The allocated budget for this project is $80,000 and includes toddler play equipment and school-aged playground. 

The scope of work and complete detail are in the attached RFP document.

Schedule:

Issued: Friday, December 17, 2021
Questions Due: Wednesday, January 12, 2022
Proposals Due: Friday, January 21, 2022
Anticipated Notice of Intention to Award: No later than February 4, 2022
Anticipated City Board of Finance Review: February 7, 2022
Contract Signing: February 8, 2022
Construction Start: March or April 2022 (as weather permits)
Construction Complete: June 30, 2022

 

Contact:

Proposals and questions shall be submitted via e-mail to:
Max Madalinski,
Parks Project Coordinator
Burlington Parks, Recreation & Waterfront
mmadalinski@burlingtonvt.gov
(802)881-4000

RFP Deadline: 
Friday, January 21, 2022