City of Burlington, Vermont City of Burlington, Vermont

Water Quality, Main Breaks & Billing: 863-4501/EMAIL

Snow Ban Line: 658-SNOW

DPW Customer Service: 863-9094/EMAIL

 

Construction Updates

Looking for updates on some of the major construction projects happening in the City this summer?
 
Current and Past Updates:
 

Construction Update 05/26/2017

Project: CY17 Street Reconstruction

Description:   Repaving of City streets as identified in the following Approved CY17 Street Reconstruction Program.  Projected roads pending commission approval to be repaired in FY17 can be found below as well.

Schedule:        April 17th, 2017 through October 15th, 2017

Activities:        The contractor is scheduled to complete CY17 paving by October 15th, 2017. All roads have been resurfaced, line-striping and cleanup will be complete this week.

Traffic:            Local traffic will be maintained with on-site traffic control and signage

CY'17 Paving - Mill & Fill

Street Name

Section of Street

PCI

Width

Length

Type of Work

MANHATTAN

ROSE-PARK

50

30

0.16

Mill and Fill

EAST AVE

COLCHESTER-MAIN ST

47

24

0.74

Mill and Fill

BELTLINE

NEW PAVEMENT – HEINEBERG BRIDGE

33-55

40

2.86

Mill and Fill

BELTLINE RAMP

PLATTSBURGH AVE

50

40

0.27

Mill and Fill

Total

 

 

 

4.03

MILES Mill/Fill

 

CY'17 Paving - Reclaim

Street Name

Section of Street

PCI

Width

Length

Type of Work

MARBLE

ALL

54

26

0.17

Reclaim

KING

BATTERY – PINE

38

35

0.20

Reclaim

VALADE

ALL

41

24

0.22

Reclaim

BORESTONE

ALL

42

25

0.15

Reclaim

RIVERS EDGE

ALL

55

32

0.22

Reclaim

HILDRED

ALL/CIRCLE

28

30

0.30

Reclaim

Total

 

 

 

1.26

MILES Reclaim

 

Project: Sidewalk Reconstruction

Description:  Installation and reconstruction of new sidewalk around the City of Burlington. 

Schedule: May through November 2017

Activities:   This is the anticipated work plan for this year. It is possible as work progresses through the season that one or more of the sidewalks on this list may not be repaired/replaced until Spring of 2018.

Street Name Start End Side

Chase

46 Chase

Colchester Av

NW

Colchester Av

Kampus Kitchen

East University Rd Driveway

S

Colchester Av

Across Barrett

Across Chase

W

N Willard

North St

Loomis

W

Isham

Loomis

Hickok Pl

W

Booth

Loomis

North St

E

School

North St

Loomis

W

Germain

Archibald

Pomeroy

W

N Union

North St

N Winooski Av

E

N Winooski Av

N Union

Archibald

E

Luck

St Marys

Intervale Av

S

Billings Ct

Billings Ct End

Van Patten Pkwy

W

Elm Terr

Elm Terr End

25 Elm Terr

S

Elm Terr

31 Elm Terr

S Winooski Av

S

Gove Ct

Shelburne Rd

Gove Ct End

N

King

S Winooski Av

Church

N

Kingsland Terr

Kingsland Terr End

S Union

N

Ledge Rd

Edgewood Ln

Iranistan Rd

N

Oakcrest Dr

Beachcrest Dr

Tallwood Ln

S

S Prospect

178 S Prospect

Main

E

S Union

Bayview

Cliff

E

S Union

Cliff

Spruce

E

S Williams

College

Main

W

Sandy Ln

Ethan Allen Pkwy

Roseade Pkwy

N

Spruce

S Union

S Willard

S

Tallwood Ln

Oakcrest Dr

Woodridge Dr

W

Woodbury Rd

Stanbury Rd

North Av

S

Project: Pavement Preservation

Description:   Application of crack sealing along various City streets to improve performance and slow deterioration of pavement.

Schedule:        July 10th through August 11th, 2017

Activities:        Work will consist of cleaning roadway of debris, then applying a crack sealing compound along existing cracks in the road surface. Traffic control will be present to direct traffic around work activities.  Various streets will be posted no parking as the contractor completes the work.  A list of streets and approximate time they will be closed to parking can be found below. This list is subject to change based on the contractor’s progress. It is anticipated crack sealing will occur on the following streets, however not all may be completed in this calendar year.

Traffic:            Local traffic will be maintained with on-site traffic control and signage.

Street Name

Section of Street

PCI

Width

Length

Unit

GAZO AVE

ALL

59-86

30

1,372

feet

MATTHEW AVE

BATTERY – PINE

78

30

739

feet

JAMES AVE

ALL

100

30

1,531

feet

RANDY LANE

ALL

61-71

30

1,531

feet

CHARITY STREET

ALL

61

30

581

feet

FAITH STREET

ALL/CIRCLE

77

30

1,003

feet

YORK DRIVE

ALL

73

30

422

feet

WESTERN AVE

ALL

88

30

1,056

feet

STANIFORD RD

ALL

61-100

30

2,666

feet

OAK STREET

ALL

69

26

1,162

feet

ARCHIBALD STREET

ALL

23-30

23-30

3,210

feet

INTERVALE AVE

ARCHIBALD – RIVERSIDE

78

30

700

feet

BATTERY STREET

MAPLE – PARK

72-85

46-50

2,680

feet

CONVERSE CT

ALL

60

26

475

feet

SHORE RD

NORTH AVE – DALE RD

77-100

30

3,432

feet

S. WILLIAMS

MAIN ST – PEARL ST

97

25

1,637

feet

LEDGE RD

ALL

81-85

25-26

1,737

feet

Total

 

 

25,934

FEET

 

Project: Parking Garage Repair Project

Description:   Phase 2 of Repair work being done within the College Street Parking Garages.

Schedule:        April 11th through September 22, 2017

Activities:        Phase 2 work includes concrete demo and repair on the 3 lower levels of the parking garage, replacement of the lights with LED fixtures, new conduit, drainage system improvements, new HVAC, and generator.

Traffic:            Both the College Street, and Battery Street entrances to the garage are closed during the first few phases of work. The College St entrance will be closed until middle of August, and Battery Street entrance until the end of August. Various stair towers are also closed. There is limited parking in this facility and access is exclusively through the Lakeview Parking Garage entrance on Cherry Street and use of the pass through between the two garages. 

Please contact DPW Customer Service if you have any project specific questions at 863-9094.

Also check updates on other projects for this summer at Parks & Recreation at HERE.