Having a successful development project requires planning -
planning what you want to do, planning for the time and money it will take to
get all your permits, planning the construction schedule, and finally planning
for the time it will take to button everything up at the end. Below is a
description of several ways we can help you plan your project before you've
invested alot of time and money and before you have applied for your
Zoning Permit, and a quick head's-up about fees and timelines so you can
plan your budget and schedule.
Pre-Application Staff Review
Applicants for all types of development are strongly
encouraged to discuss their proposals with zoning staff prior
to the submission of an application. This gives us an opportunity to have an
informal conversation with you about your project before you've invested a
lot of time and money, offer suggestions that may make the project easier
to accomplish, tell you what information you will need when you are ready to
apply for your permit, and to help you understand what you might expect from
the application review process. This can be done by simply stopping in our
office during business hours, or better yet calling ahead to make an
appointment with one of our planners. We are more than happy to meet for a
pre-application meeting as this generally makes the process easier for
everybody!
Pre-Application Neighborhood Public Meeting
Major Impact applications are required to complete an additional step prior to application per Section 3.2.1(d) of the CDO. Pre-Application Neighborhood Public Meetings are intended to provide an opportunity for:
- Residents to become aware of new development projects proposed in their neighborhood at an early stage of its coneptual design;
- Residents and applicants to meet and discuss proposed developments; and,
- The applicant to take into consideration neighborhood feedback on a proposed development.
This community dialogue takes place
entirely outside of the formal public hearing process and well in advance of
incurring major detailed design and engineering expenses. While feedback from
the neighborhood is not binding on the applicant, an open and collaborative
dialogue is expected. A clear understanding of the project and of potential
issues and opportunities will benefit both applicant and neighbors alike during
the application review process. For more details on this process, please
review Pre-Application Neighborhood Meeting Guide.
Sketch Plan
Review
Upon request (and required under Article 10 -
Subdivision or Article 11 - Planned Development of the Comprehensive Development Ordinance) a
Sketch Plan Review may be scheduled before the Development Review Board and/or
the Design Advisory Board prior to the submission of an application. Like the
pre-application staff review above this gives the DRB and DAB an opportunity
to have an informal conversation with you about your project before you've
invested a lot of time and money, and offer suggestions that may make the
project easier to accomplish.
Technical Review
Committee
Finally, at the discretion of the Zoning
Administrator, a pre-application review may be scheduled before the City's
Technical Review Committee (TRC) for any projects that will require review
under the Major Impact (Article 3, Part 5), Subdivision (Article 10) and/or
Planned Development (Article 11) provisions of the CDO, or for any project
that, in the opinion of the Zoning Administrator due to its size and/or
complexity, would benefit from an informal review by a cross-section of City
Departments. Representatives from Planning & Zoning, Public Works, Code
Enforcement, Burlington Electric, CEDO Burlington Fire, and Parks &
Recreation participate. This is a great opportunity to share information about
large and more complex project across several City departments, and can be a
huge help to you in navigating the permitting process.
Fees
Keep in mind there are a variety of fees that
are required including when you :
- Apply for the Zoning Permit | Zoning
Permit Fees |,
- Apply for the Construction Permit (from DPW -
Inspection Services),
- Pick up your final Zoning Permit (applicable only
for larger projects),
- Request a Final Certificate of Occupancy
Inspection the project to confirm that the project was built as permitted | Code
Enforcement Fees |, and
- Require any additional Certificate of
Occupancy Inspections (because the initial inspection found your project
incomplete or not in compliance with your Zoning Permit).
Timing
- Zoning Permit applications that are
reviewed by staff can take up to 30-days, but usually take only a few days,
depending on the complexity of the project and staff workloads.
- Zoning
Permit applications that are reviewed by the Development Review Board can take
8 weeks or longer depending on the complexity of the project and the DRB's
schedule.
- Once a decision has been made on any Zoning Permit
application, there is a state-mandated appeal period (15-days for staff
decisions, 30-days for DRB decisions) before you can receive your permit and
apply for your Construction Permit.
- Work under a Zoning Permit must be
started within 1 year of the permit decision.
- Work under a Zoning
Permit must be completed and a Final Certificate of Occupancy issued within 2
years of the permit decision.