Process
The plan activities and timeline are summarized in the table below. For more detailed information on each task and sub-task identified in the Scope of Work, please see the Detailed Downtown & Waterfront Plan Scope of Work. The blue highlight indicates the current phase of the project.
Plan BTV Activities
|
| Activities 2 & 3 - MASTER PLANNING PROCESS AND CODE DEVELOPMENT - To be Completed by Summer 2012
The public engagement process has begun!
Check out our Public Input Web Tool and continue to give your input on the project.
Design Charrette - January 24-30, 2012
September 10, 2011 - Public Workshop - How to better connect the Waterfront to the rest of Downtown and Church Street? - Download Report.
November 2011 - Neighborhood Improvement Nights (NINs) with each Neighborhood Planning Assemblies (NPAs) - Download Report
|
|
Activity 1 - EXISTING CONDITIONS ANALYSIS - COMPLETED
Read the Phase 1 Report - Insights and Recommendations POSTER for a quick snap shot of the first Phase studies.
This first task proposes the preparation of a comprehensive inventory and assessment of existing conditions in the study area to identify the primary needs, challenges and opportunities. The following studies/analyses are under way:
|
|
|
|
|