Operation Clean Sweep is coming to Burlington April 24-May 2, 2024.
Details available at burlingtonvt.gov/dpw/clean-sweep
Great Streets Main Street Construction info availalble at greatstreetsbtv.com/main-street.
Great Streets Main Street Construction info availalble at greatstreetsbtv.com/main-street.
PROJECT BACKGROUND The Great Streets Initiative is a culmination of many years of planning and project development to reinvest in our core downtown streets, continue beautifying our streetscape and installing more sustainable infrastructure. The process began with the public vote in March of 2015 to use the City's downtown TIF district to make new investments in the downtown's public infrastructure and to ensure that Burlington has a downtown that is a vibrant, walkable and sustainable urban center. On August 13, 2018, City Council approved the contract to begin work. For information on the overall Great Streets concept, please visit www.greatstreetsBTV.com.
TENTATIVE SCHEDULE
4/2019-Early October (northern block largely reopened) - Complete Construction.
Here is a copy of the presentation we shared in March 2019 with local businesses. Some of this is subject to change.
Here is a copy of the presentation (some of which is likely to change) we shared in August 2018 with local businesses and residents along the impacted St. Paul corridor.
PROJECT DESCRIPTION Work will include reconstruction of St Paul from Main to Maple, including the intersections with King and Maple and extend slightly along each side street. The project will work to underground overhead utilities through construction of a new duct bank under the western sidewalk, install new tree infrastructure, sidewalks, tree belts, pervious pavers, stormwater gardens, drainage, curbs and repaving the surface of the road. We will have full time on-site inspection of the work and representation for the City that residents and businesses will be able to reach out to regarding immediate construction concerns.
IMPACTS - tentative
PARKING - tentative
DELIVERIES
ORDER OF WORK
Light Poles
Stormwater
Soil Cells
Waterline Install (Maple/St. Paul)
Road Demo (lower block)
Tree Planting
Granite Curbs
Asphalt (lower block)
Sidewalks (mid June - end of August)
Pavers
Bike Racks
Final Layer of Asphalt and Line Striping
PROJECT TEAM